# Bill Of Materials
|
|
|
|
At the heart of the Manufacturing system is the **Bill of Materials** (BOM).
|
|
The **BOM** is a list of all materials (either bought or made) and operations
|
|
that go into a finished product or sub-Item. In ERPNext, the component could
|
|
have its own BOM hence forming a tree of Items with multiple levels.
|
|
|
|
<div class="embed-container">
|
|
<iframe width="560" height="315" src="https://www.youtube.com/embed/9J9QBYBpD0M?rel=0" frameborder="0" allow="autoplay; encrypted-media" allowfullscreen>
|
|
</iframe>
|
|
</div>
|
|
|
|
|
|
To make accurate Purchase Requests, you must always maintain correct BOMs.
|
|
To make a new BOM:
|
|
|
|
> Manufacturing > Bill of Materials > New BOM
|
|
|
|
<img class="screenshot" alt="Task" src="{{docs_base_url}}/assets/img/manufacturing/bom.png">
|
|
|
|
* To add Operations select 'With Operation'. The Operations table shall appear.
|
|
|
|
<img class="screenshot" alt="Task" src="{{docs_base_url}}/assets/img/manufacturing/bom-operations.png">
|
|
|
|
* Select the Item for which you want to make the BOM.
|
|
* Add the operations that you have to go through to make that particular Item in the “Operations” table. For each operation, you will be asked to enter a Workstation. You must create new Workstations as and when necessary.
|
|
* Workstations are defined only for product costing and Work Order Operations scheduling purposes not inventory.
|
|
* Inventory is tracked in Warehouses not Workstations.
|
|
|
|
###Costing of a BOM
|
|
|
|
* The Costing section in BOM gives an approximate cost of producing the Item.
|
|
|
|
* Add the list of Items you require for each operation, with its quantity. This Item could be a purchased Item or a sub-assembly with its own BOM. If the row Item is a manufactured Item and has multiple BOMs, select the appropriate BOM. You can also define if a part of the Item goes into scrap.
|
|
|
|
<img class="screenshot" alt="Costing" src="{{docs_base_url}}/assets/img/manufacturing/bom-costing.png">
|
|
|
|
* This cost can be updated on by using the 'Update Cost' button.
|
|
|
|
<img class="screenshot" alt="Update Cost" src="{{docs_base_url}}/assets/img/manufacturing/bom-update-cost.png">
|
|
|
|
* User can select the currency in the BOM
|
|
* System calculates the costing based on the price list currency
|
|
|
|
<img class="screenshot" alt="Update Cost" src="{{docs_base_url}}/assets/img/manufacturing/price-list-based-currency-bom.png">
|
|
|
|
### Materials Required(exploded)
|
|
|
|
This table lists down all the Material required for the Item to be Manufactured.
|
|
It also fetches sub-assemblies along with the quantity.
|
|
|
|
<img class="screenshot" alt="Exploded Section" src="{{docs_base_url}}/assets/img/manufacturing/bom-exploded.png">
|
|
|
|