* Source Warehouses: The warehouse where you store your raw materials. Each required item can have separate source warehouse. Group warehouse also can be selected as source warehouse. On submission of Work Order, the raw mateirals will be reserved in these warehouses for production usage.
* Work-in-Progress Warehouse: The warehouse where your Items will be transferred when you begin production. Group Warehouse can also be selected as Work-in-Progress warehouse.
* Target Warehouse: The warehouse where you store finished Items before they are shipped.
* Scrap Warehouse: Scrap Items will be stored in this warehouse.
* Required Items: All the required items (raw materials) will be fetched from BOM and populated in this table. Here you can also change the default source warehouse for any item. And during the production, you can track transferred raw materials from this table.
* When a Work Order is submitted, based on the Planned Start Date and the availability of the workstations, system schedules all operations for the Work Order (if Work Order has operations specified).
* Once you have submitted your Work Order, you need to Transfer the Raw Materials to initiate the Manufacturing Process.
* This will create a Stock Entry with all the Items required to complete this Work Order to be added to the WIP Warehouse. (this will add sub-Items with BOM as one Item or explode their children based on your setting above).
* If the responsibility for Material Transfer and Production Entry lies with two separate users
If this is the case, you can select the Skip Material Transfer check box, which will allow you to make the “Manufacture” Stock Entry directly by clicking on the ‘Finish’ button.
1. On Submitting the Work Order, the system will reserve a slot for each of the Work Order Operations serially after the planned start date based on the workstation availability. The Workstation availability depends on the Workstation timings, holiday list and if some other Work Order Operation was scheduled in that slot. You can mention the number of days for the system to try scheduling the operations in the Manufacturing Settings. This is set to 30 Days by default. If the operation requires time exceeding the available slot, system shall ask you to break the operations. Once the scheduling is done system shall create Time Logs and save them. You can Modify them and submit them later.
3. Transfer Raw Material: This will create a Stock Entry with all the Items required to complete this Work Order to be added to the WIP Warehouse. (this will add sub-Items with BOM as one Item or explode their children based on your setting above).
4. Update Finished Goods: This will create a Stock Entry that will deduct all the sub-Items from the WIP Warehouse and add them to the Finished Goods Warehouse.