unnecessary requirement for project creation as this is a field of the Type select which will be pre-filled. When creating a project of list view it will also bring up this field as it has "reqd": 1. A new projekt will have the status set to open in most cases.
Co-authored-by: Nabin Hait <nabinhait@gmail.com>
Co-authored-by: Himanshu <himanshuwarekar@yahoo.com>
* fix: task validation error when adding tasks to projects
When adding a task to a project, if the project didn't have an Expected End Date the validation would fail.
This is because passing a None value to getdate() returns today's date, rather than being optional as expected.
* update task.py
* feat: create a duplicate project
* fix: allow duplication via form
* feat: fetch old task and link project
* fix: link task with project
* fix: parse json string as python object
* fix: avoid duplicate task based on the project template
* fix: ask user for the new project name
* fix: display a descriptive message on switching to a new route
* fix: override duplicate in menu
* fix: check for duplicate project name after submitting prompt
* fix: set the project template
* fix: minor changes
* fix: function call
* refactor: add a separate button for duplicate
* Update project.js
* feat: Add default energy point rules during install
* fix: Add completed_by field to task doctype
* fix: Rule data
* fix: Add default rules for opportunity
* fix: Add a patch to create default energy point rules
* fix: Default success action message
* fix: Use .items() instead of .iteritems()
* fix: Add "create_default_energy_points" patch entry
* fix: Reload Energy Point Rule to fix patch
* fix: Import frappe
- Case: If the company had standard working hour set
and when the user creates a timesheet with same date for
"To" and "From" then the hours field automatically used to
get reset to 0 after saving the form.
* fix: merge conflict
* fix: restored missing set_gst_state_and_state_number function
* fix: style linting as per codacy
* fix: Fixes related to customer/lead merging
* fix: merge conflict
* fix: Fixes related to customer/lead merging
* fix: Assign isue/opportunity to user
* fix: Assign isue/opportunity to user
* fix: Replaced Invoice type by GST Category
* fix: merge conflict
* fix: merge conflict
* fix: test cases
* fix: test cases
> moved all auto attendance settings from HR Settings to shift
> added shift in attendance and Employee Attendance Log
> reordered and cleaned up fields in HR Settings and Employee DocType
When tasks are imported with their Project set, import slows down as
number of tasks increase. This is largely due to `load_tasks` being
called in Project which is only required when Form loads. So, we can
skip it during import.
Also, converted some get_doc calls to get_cached_doc.