validation added to prevent Delivery Date in Porduction Order to be lesser than Planned Start Date
This commit is contained in:
parent
381a9377d9
commit
fc595064e0
@ -309,10 +309,9 @@ class ProductionOrder(Document):
|
||||
self.actual_end_date = None
|
||||
|
||||
def validate_delivery_date(self):
|
||||
if self.docstatus==1:
|
||||
if self.planned_end_date and self.expected_delivery_date \
|
||||
and getdate(self.expected_delivery_date) < getdate(self.planned_end_date):
|
||||
frappe.msgprint(_("Production might not be able to finish by the Expected Delivery Date."))
|
||||
if self.planned_start_date and self.expected_delivery_date \
|
||||
and getdate(self.expected_delivery_date) < getdate(self.planned_start_date):
|
||||
frappe.throw(_("Expected Delivery Date must be greater than Planned Start Date."))
|
||||
|
||||