# Capacity Planning based on Production Order
|
|||
|
|
|||
|
Capacity Planning functionality helps you in tracking production jobs allocated on each Workstation.
|
|||
|
|
|||
|
<img alt="Role Desk Permission" class="screenshot" src="/docs/assets/img/articles/capacity-1.png">
|
|||
|
|
|||
|
Follow are the steps to use Capacity Planning Feature in your ERPNext account.
|
|||
|
|
|||
|
1. Operations
|
|||
|
|
|||
|
To add operations, go to:
|
|||
|
|
|||
|
`Manufacturing > Bill of Materials > Operations`
|
|||
|
|
|||
|
2. Workstation
|
|||
|
|
|||
|
Add each Workstation in your ERPNext account from:
|
|||
|
|
|||
|
`Manufacturing > Bill of Materials > Workstation`
|
|||
|
|
|||
|
In the Workstation master, you can define which operations will be performed on it, what are the cost associated with it, and what are the working hours of that Workstation.
|
|||
|
|
|||
|
3. Bill of Materials (BOM):
|
|||
|
|
|||
|
In a BOM, with the list of raw material needed, for manufacturing, you can also list operation and workstations through which those raw materials will be processed.
|
|||
|
|
|||
|
4. Production Order:
|
|||
|
|
|||
|
On submission of Production Order, Timesheet for Operations. This helps you allocate production jobs on each Workstation, as well as you can update actual time taken for each Operation.
|
|||
|
|
|||
|
### Error due to Capacity Planning
|
|||
|
|
|||
|
**Question:** On Submission of Production Order, we are getting following error message.
|
|||
|
|
|||
|
<img alt="Role Desk Permission" class="screenshot" src="/docs/assets/img/articles/capacity-2.png">
|
|||
|
|
|||
|
**Answer: **Please check if you have updated Working Hours in the Workstation master? If not, then please update it and then try to submit Production Order.
|
|||
|
|
|||
|
On submission of Production Order, Operations (as added in the BOM) are allocated on the workstation. Each operation should start and end on the same day. If a system is not able to schedule that operation in a day, then system request you to divide that Project, so that system can allocate smaller operations in a day.
|
|||
|
|
|||
|
If you have update working hours in the Workstation, but still getting this issue, that because one of your operation is taking too long, and cannot be completed in a day. Please divide that operation into smaller operations, so that it can be allocated on Workstation and completed on the same day.
|
|||
|
|
|||
|
### Avoid Working Hours of Workstation
|
|||
|
|
|||
|
If you want to ignore above validation and allow scheduling of production job beyond the working hours of the Workstation, enable
|
|||
|
Overtime in the Manufacturing Settings.
|
|||
|
|
|||
|
<img alt="Role Desk Permission" class="screenshot" src="/docs/assets/img/articles/capacity-3.png">
|
|||
|
|
|||
|
If you want to complete disable Capacity Planning feature, in the Manufacturing Settings, check field "Disable Capacity Planning and Time Tracking".
|
|||
|
|