Production Planning Tool helps you plan production and purchase of Items for a
|
||
|
period (usually a week or a month).
|
||
|
|
||
|
This list of Items can be generated from the open Sales Orders in the system
|
||
|
and will generate:
|
||
|
|
||
|
* Production Orders for each Item.
|
||
|
* Purchase Requests for Items whose Projected Quantity is likely to fall below zero.
|
||
|
|
||
|
To use the Production Planning Tool, go to:
|
||
|
|
||
|
> Manufacturing > Tools > Production Planning Tool
|
||
|
|
||
|
<img class="screenshot" alt="Production Planing Tool" src="/assets/manual_erpnext_com/img/manufacturing/ppt.png">
|
||
|
|
||
|
|
||
|
|
||
|
#### Step 1: Select and get Sales Order
|
||
|
|
||
|
* Select sales orders for MRP using filters (Time, Item, and Customer)
|
||
|
* Click on Get Sales Order to generate a list.
|
||
|
|
||
|
<img class="screenshot" alt="Production Planing Tool" src="/assets/manual_erpnext_com/img/manufacturing/ppt-get-sales-orders.png">
|
||
|
|
||
|
|
||
|
|
||
|
#### Step 2: Get Item from Sales Orders.
|
||
|
|
||
|
You can add/remove or change quantity of these Items.
|
||
|
|
||
|
<img class="screenshot" alt="Production Planing Tool" src="/assets/manual_erpnext_com/img/manufacturing/ppt-get-item.png">
|
||
|
|
||
|
#### Step 3: Create Production Orders
|
||
|
|
||
|
<img class="screenshot" alt="Production Planing Tool" src="/assets/manual_erpnext_com/img/manufacturing/ppt-create-production-order.png">
|
||
|
|
||
|
|
||
|
|
||
|
#### Step 4: Create Material Request
|
||
|
|
||
|
Create Material Request for Items with projected shortfall.
|
||
|
|
||
|
<img class="screenshot" alt="Production Planing Tool" src="/assets/manual_erpnext_com/img/manufacturing/ppt-create-material-request.png">
|
||
|
|
||
|
|
||
|
|
||
|
The Production Planning Tool is used in two stages:
|
||
|
|
||
|
* Selection of Open Sales Orders for the period based on “Expected Delivery Date”.
|
||
|
* Selection of Items from those Sales Orders.
|
||
|
|
||
|
The tool will update if you have already created Production Orders for a
|
||
|
particular Item against its Sales Order (“Planned Quantity”).
|
||
|
|
||
|
You can always edit the Item list and increase / reduce quantities to plan
|
||
|
your production.
|
||
|
|
||
|
> Note: How do you change a Production Plan? The output of the Production
|
||
|
Planning Tool is the Production Order. Once your orders are created, you can
|
||
|
change them by amending the Production Orders.
|
||
|
|
||
|